Application of the horizontal jet grouting pile in water-bearing sandy layer of shallow excavating tunnel

ZHOU Qian, ZHAO Degang   

  1. Guangzhou Metro Design & Research Institute Co., Ltd, Guangzhou 510000, Guangdong, China
  • Received:2014-05-19 Revised:2014-07-02 Published:2014-05-19

Abstract: The construction process of a shallow buried tunnel crossing the water rich sand layer was analyzed in Shenzhen by 3-D numerical simulation, the deformation and the stress of the surrounding rock were discussed under the circumstances of using horizontal jet grouting pile or not in the process of excavating. Based on the numerical simulation and the measurement results, a conclusion could be drawn that the application of the horizontal jet grouting pile had significant effect in controlling the deformation, the subsidence of support and the stress of support. Furthermore, some solutions were put forth to some problems in the construction of horizontal jet grouting pile and the direction of the development. The obtained conclusions could provide experience and numerical support for the design and construction of the similar situation.

Key words: water-bearing sandy layer, horizontal jet grouting pile, shallow excavating tunnel, numerical simulation, monitoring and measurement

CLC Number: 

  • U451.2
[1] 沈尧兴.地铁富水软弱地层连拱隧道的非降水施工技术[D].成都:西南交通大学,2003. SHEN Yaoxing. Non-precipitation construction technique study on subway multi-archy tunneling by excavation in watery strata[D].Chengdu:Southwest Jiaotong University, 2003.
[2] 吉小明,吕纬.含水砂层隧道围岩失稳破坏机制及控制研究现状综述[J].岩土力学,2009, 30(增2):291-296. JI Xiaoming, LYU Wei. Review of research on instability failure mechanism and stability control of tunnel surrounding rock in water-bearing sandy ground[J]. Rock and Soil Mechanics, 2009, 30(S2):291-296.
[3] 张民庆,张文强,孙国庆.注浆效果检查评定技术与应用实例[J].岩石力学与工程学报,2006,25(增2):3909-3918. ZHANG Minqing, ZHANG Wenqiang, SUN Guoqing. Evaluation technique of grouting effect and its application to engineering[J]. Chinese Journal of Rock Mechanics and Engineering, 2006, 25(S2):3909-3918.
[4] 吕玺琳,黄茂松,钱建固. 基于非共轴本构模型的砂土真三轴试验分叉分析[J].岩土工程学报,2008,30(5):647-651. LYU Xilin, HUANG Maosong, QIAN Jiangu. Bifurcation analysis in ture traxial tests on sands based on non-coaxial elasto-plasticity model[J]. Chinese Journal of Geotechical Engineering, 2008, 30(5):647-651.
[5] 魏星,沈乐,陶志平. 富水软岩隧道突泥塌方及地层沉降的模型实验[J]. 岩土力学, 2012,33(8):2291-2296. WEI Xing, SHEN Le, TAO Zhiping. Model test studies of collapse and settlement of tunnel in saturated soft rocks[J]. Rock and Soil Mechanics, 2012, 33(8):2291-2296.
[6] 施成华,彭立敏,赵丹.考虑时空效应的隧道开挖及降水引起的地层变形计算[J].土木工程学报,2008,41(12):91-96. SHI Chenghua, PENG Limin, ZHAO Dan. Calculation of stratum deformation caused by tunnel excavation and dewatering[J].China Civil Engineering Journal, 2008, 41(12):91-96.
[7] 周健,姚志雄,张刚.砂土渗流过程的细观数值模拟[J].岩土工程学报,2007,29(7):977-981. ZHOU Jian, YAO Zhixiong, ZHANG Gang. Mesomechanical simulation of seepage flow in sandy soil[J]. Rock and Soil Mechanics, 2007, 29(7):977-981.
[8] 任伟新.二重管无收缩双液注浆在饱和动态含水砂层浅埋暗挖隧道中的应用[J].施工技术,2009,36(6):84-87 REN Weixin. Application of double pipe and non-shrinkage double liquid grouting on shallow bored tunnel in saturated dynamic water-bearing sandy Layer[J].Constuction Technology, 2009, 36(6):84-87.
[9] 于忠波,李世君,施龙焱.水平旋喷技术在软岩富水地铁隧道中的应用及优化[J].隧道建设,2012,32(3):377-382. YU Zhongbo, LI Shijun, SHI Longyan. Application and optimization of horizontal jet grouting piles in construction of tunnels in water-rich soft rock ground[J]. Tunnel Construction, 2012, 32(3):377-382.
[10] 刘勇,孙星亮,朱永全,等.水平旋喷预支护技术在铁路隧道中的应用[J].岩石力学与工程学报,2002,21(6):905-909.
[11] 郭亮,肖晓春,黄均龙,等.高压旋喷工艺中喷射流切割效果影响因素的研究[J].地下空间与工程学报,2008,(5):937-942. GUO Liang, XIAO Xiaochun, HUANG Junlong, etc. Study on factors for cutting effect of high pressure jet flow in jet grouting[J]. Underground Space and Engineering, 2008, (5):937-942.
[12] 白聚敏.软流塑地层暗挖隧道的水平旋喷注浆[J].隧道建设,2008,28(4):498-500. BAI Jumin. Horizontal jet grouting for mined tunnel in soft rheologic-plastic ground[J]. Tunnel Construction, 2008, 28(4):498-500.
[13] 孙国庆,殷九荣.水平旋喷加固在富水未成岩粉细砂层中的应用[J]. 隧道建设,2012,32(2):213-217. SUN Guoqing, YIN Jiurong. Application of horizontal jet grouting in water-rich immature fine silty sand strata[J]. Tunnel Construction, 2012, 32(2):213-217.
[14] 王绍君,刘宗仁,陶夏新.浅埋暗挖隧道施工性态的数值模拟与分析[J].土木工程学报,2007,40(6):75-79. WANG Shaojun, LIU Zongren, TAO Xiaxin. Numerical simulation analysis of construction behavior of shallow tunneling by excavation[J].Civil Engineering, 2007, 40(6):75-79.
[15] 赵旭峰,王春苗.厦门海底隧道陆域浅埋段动态施工过程分析[J].地下空间与工程学报,2009,5(8):769-775. ZHAO Xufeng, WANG Chunmiao. Dynamic construction mechanics analysis of xiamen sub-sea tunnel in terrestrial shallow section[J].Underground Space and Engineering, 2009, 5(8):769-775.
[16] 路德富.水平高压旋喷注浆技术在城市浅埋隧道预支护中的应用[J].西部探矿工程,2008(2):72-74. LU Defu. Application of horizontal high-pressure Jet-grouting technique for pre-support in urban shallow tunnels[J]. West-China Exploration Engineering, 2008(2):72-74.
[17] 仝学让,薛模美.水平旋喷桩在地铁暗挖隧道施工中的应用[J].现代隧道技术,2003,40(3):51-54. TONG Xuerang, XUE Momei.Application of horizontal rotary jet-grouting piles to metro built by mining method[J]. Modern Tunnelling Technology, 2003, 40(3):51-54.
[18] 黎中银.水平高压旋喷工法在预加固工程中的应用研究[D].北京:中国地质大学,2009. LI Zhongyin. Application of horizontal jet-grouting at pre-reinforcing construction[D].Beijing:China University of Geosciences, 2009.
[19] 周小文,濮家骝.砂土中隧洞开挖引起的地面沉降试验研究[J]. 岩土力学,2002,23(5):559-563. ZHOU Xiaowen, PU Jialiu. Centrifuge model test on ground settlement induced by tunneling sandy soil[J]. Rock and Soil Mechanics, 2002, 23(5):559-563.
[20] 孙星亮,王海珍.水平旋喷固结体力学性能试验及分析[J]. 岩石力学与工程学报,2003,22(10):1695-1698. SUN Xingliang, WANG Haizhen. Testing on physical and mechanical properties of horizontal jet-grouted soilcrete[J]. Chinese Journal of Rock Mechanics and Engineering, 2003, 22(10):1695-1698. [21] 孟凤朝.深圳地铁大-科区间隧道水平旋喷桩施工技术[J]. 铁道工程学报,2003,78(2):1-4. MENG Fengchao. Construction technique of horizontal rotary-sprayed piles in tunnel at major theatre-science museum section of shenzhen subway[J]. Journal of Railway Engineering Society, 2003, 78(2):1-4.
[22] 吴波,高波,骆建军.地铁区间隧道水平旋喷预加固效果数值模拟[J].西南交通大学学报,2004,39(5):605-608. WU Bo, Gao Bo, LUO Jianjun.Numerical simulation of reinforcing effect of horizontal drilling jet grounding pegs on shenzhen metro tunnel between sations[J]. Journal of Southwest Jiaotong University, 2004, 39(5):605-608.
[23] 吉小明,谭文.饱和含水砂层地下水渗流对隧道围岩加固效果的影响研究[J].岩石力学与工程学报,2010,29(增2):3655-3662. JI Xiaoming, TAN Wen. Study of influence of groundwater seepage on reinforcement effect of tunnel surrounding rock in saturated water-bearing sand layer[J]. Chinese Journal of Rock Mechanics and Engineering, 2010, 29(S2):3655-3662.
[24] 李术才, 朱维申, 陈卫忠, 等. 弹塑性大位移有限元方法在软岩隧道变形预估系统研究中的应用[J]. 岩石力学与工程学报, 2002, 21(4):466-470.
[25] 刘钟,柳建国,张义,等.隧道全方位高压喷射注浆拱棚超前支护新技术[J].岩土力学与工程学报,2009,28(1):59-65. LIU Zhong, LIU Jianguo, ZHANG Yi, et al. New technique of fotary horizontal jet grouting for arched tunnel pre-support[J].Chinese Journal of Rock Mechanics and Engineering, 2009, 28(1):59-65.
[1] SONG Guijie. Deformation characteristic and instability analysis for shallow soft rock section during tunnel-entering construction [J]. JOURNAL OF SHANDONG UNIVERSITY (ENGINEERING SCIENCE), 2018, 48(2): 53-60.
[2] WANG Danhua, ZHANG Guanmin, LENG Xueli, XU Mengna, HAN Yuanyuan. The numerical simulation of two-phase flow distribution characteristics in T-tube [J]. JOURNAL OF SHANDONG UNIVERSITY (ENGINEERING SCIENCE), 2018, 48(1): 89-95.
[3] XIA Mengran, LI Wei, FENG Xiao, ZHU Guangxuan, LI Xia. Grouting reinforcement and excavation stability on super-shallow buried and water-rich sand stratum subway transverse channel [J]. JOURNAL OF SHANDONG UNIVERSITY (ENGINEERING SCIENCE), 2017, 47(2): 47-54.
[4] LYU Guoren, ZHANG Qun, NIU Ben, GAO Quanting, WU Zhaoshou. The effects of pile foundation of high-rise building on adjacent structures [J]. JOURNAL OF SHANDONG UNIVERSITY (ENGINEERING SCIENCE), 2017, 47(1): 48-58.
[5] PENG Yuancheng, DONG Xu, LIANG Na, DENG Zhenquan. Model test of the Beipan River's new open-web continuous rigid frame bridge corner node [J]. JOURNAL OF SHANDONG UNIVERSITY (ENGINEERING SCIENCE), 2016, 46(6): 113-119.
[6] MI Chunrong, LI Jianming. Development and application of after grouting device for prestressed concrete pipe pile [J]. JOURNAL OF SHANDONG UNIVERSITY (ENGINEERING SCIENCE), 2016, 46(4): 89-95.
[7] TANG Weize, OU Jinqiu, CUI Xinzhuang, LOU Junjie, XIAO Ming, ZHANG Jiong, HUANG Dan, HOU Fei. Field test and research on vehicle load induced dynamic pore pressure in asphalt pavement [J]. JOURNAL OF SHANDONG UNIVERSITY (ENGINEERING SCIENCE), 2015, 45(6): 84-90.
[8] QIN Mingchen, DONG Yong, CUI Lin, SUI Hui, LIU Jinglong. The simulation of fluid dynamics and mass transfer in a double-loop WFGD [J]. JOURNAL OF SHANDONG UNIVERSITY (ENGINEERING SCIENCE), 2015, 45(5): 88-94.
[9] CAO Weidong, DAI Tao, YU Jinbiao, XI Kaihua, LU Tongchao, CHENG Aijie. An IMPIMC method for chemical simulation [J]. JOURNAL OF SHANDONG UNIVERSITY (ENGINEERING SCIENCE), 2015, 45(1): 88-94.
[10] GAO Zhijun, CUI Xinzhuang, SUI Wei, GUO Hong, LIU Hang, LI Changyi, FENG Hongbo. Dynamic interaction and damage analysis of large runaway vehicle and tunnel lining [J]. JOURNAL OF SHANDONG UNIVERSITY (ENGINEERING SCIENCE), 2014, 44(5): 49-57.
[11] ZHANG Tao, HAN Jitian, YAN Suying, YU Zeting, ZHOU Ran. The analysis and testing of thermal performance on solar evacuated tube [J]. JOURNAL OF SHANDONG UNIVERSITY (ENGINEERING SCIENCE), 2014, 44(4): 76-83.
[12] ZHANG Wenjun, LI Shucai, SU Maoxin*, XUE Yiguo, QIU Daohong. Detection  method of karst caves in city subway based on  the cross-hole resistivity tomography [J]. JOURNAL OF SHANDONG UNIVERSITY (ENGINEERING SCIENCE), 2014, 44(3): 75-82.
[13] LIU Yang, GE Lian-sheng*. TE mode analysis based on a new Padé approximant BPM algrorithm [J]. JOURNAL OF SHANDONG UNIVERSITY (ENGINEERING SCIENCE), 2014, 44(1): 19-23.
[14] WANG Jian-ming, PEI Xin-chao, FAN Xian-hang, LIU Wei, CAO Yan-chao. Numerical simulations of a particle impacting to affect the surface
morphology by SPH coupled FEM
[J]. JOURNAL OF SHANDONG UNIVERSITY (ENGINEERING SCIENCE), 2013, 43(5): 87-92.
[15] L Guo-ren1, SUI Bin2, WANG Yong-jin1, WU Jian-quan3. Study on numerical simulation and stability analysis shallow buried tunnel excavation under unsymmetrical  pressure [J]. JOURNAL OF SHANDONG UNIVERSITY (ENGINEERING SCIENCE), 2013, 43(4): 68-73.
Viewed
Full text


Abstract

Cited

  Shared   
  Discussed   
No Suggested Reading articles found!