Abstract:
The fault crushed zone F4-4 of the Qingdao Jiaozhou Bay subsea tunnel, is seriously influenced by the earth construction. And the stave rock, which has low intensity existence together with the high hydraulic pressure, is bad for thestability, so the possibility of waterburst under violent geological condition is high, and the construction risk is enormous. The fullface curtain grouting technical parameters was determined by onsite test.The main tunnel area grouting reinforcement was 5?m away from the tunnelexcavation contour lines. The grouting proliferation radius of the upper crosssection was 15m, and the proliferation grouting radius of the lower crosssection was 20?m. The grouting endpoint radius was 35?m, and the watercement ratio was 1∶1, and the grouting pressure was 3~4?MPa. The advancing grouting was used in constructiontechnology. Finally, the fullface curtain grouting plan and measure was successfully applied in the design and construction in the right line of the Qingdao Jiaozhou Bay subsea tunnel for passing through the No. F4-4 fault. This fullface curtain grouting has significance to similar project.
Key words: Qingdao Jiaozhou bay subsea tunnel;F4-4 waterburst fault;fullface curtain grouting
ZHAO Ji-Ceng. Study of full-face curtain grouting on water-burst fault F4-4 subsea tunnel in Qingdao Jiaozhou bay[J].JOURNAL OF SHANDONG UNIVERSITY (ENGINEERING SCIENCE), 2009, 39(6): 116-120.
0 / / Recommend
Add to citation manager EndNote|Reference Manager|ProCite|BibTeX|RefWorks
URL: http://gxbwk.njournal.sdu.edu.cn/EN/
http://gxbwk.njournal.sdu.edu.cn/EN/Y2009/V39/I6/116
Cited